Calculate cubic yards of concrete needed for any slab, footing, or pad, plus the number of 80lb pre-mix bags. Includes waste factor. Free concrete calculator for contractors.
Enter the slab length, width, and thickness in inches, then pick a waste factor. The calculator converts the pour into cubic yards of ready-mix concrete and the equivalent number of 80lb pre-mix bags, with your waste margin built in.
The concrete slab calculator estimates the volume of concrete required for a flat pour — a slab, footing, pad, sidewalk, or patio — and converts that volume into two practical order quantities: cubic yards of ready-mix concrete and the equivalent number of 80-pound bags of pre-mixed concrete. It also reports the slab’s surface area in square feet. Enter the length and width of the pour in feet and the thickness in inches, choose a waste factor, and the tool returns the numbers you need to call the ready-mix plant or load up at the home center.
The calculator works in feet and inches and outputs cubic yards and bags:
The single most common concrete-ordering mistake is mixing feet and inches. Length and width are entered in feet; thickness is entered in inches. The calculator divides thickness by 12 to convert it to feet before multiplying. If you entered thickness in feet by mistake — typing 4 instead of 4 inches (0.333 ft) — the volume would come out twelve times too large and you would order a truck you do not need. Always confirm the unit printed next to each field before you order.
Concrete volume is sold by the cubic yard. Because one cubic yard equals 3 ft × 3 ft × 3 ft = 27 cubic feet, you convert cubic feet to cubic yards by dividing by 27. The calculator applies your waste factor after the division, so the waste inflates the final order quantity rather than the raw volume. For example, 200 cubic feet ÷ 27 = 7.41 cubic yards before waste, and 7.41 × 1.10 = 8.15 cubic yards with a 10% waste factor.
The bag count assumes each 80-pound bag yields 0.6 cubic feet of finished concrete — the published yield for standard Quikrete and Sakrete 80lb mixes. Yields vary by manufacturer and mix design, so always check the yield printed on the bag or the manufacturer’s data sheet and adjust the count if you buy a different size. Common yields are:
For pours above roughly 1.5 cubic yards, ready-mix delivery is almost always cheaper and far less labor than mixing bags by hand. A single cubic yard is about 45 eighty-pound bags — that is a full day of mixing for two people, versus a 10-minute truck pour.
Pour a 30 ft × 20 ft patio slab at 4 inches thick with a 10% waste factor — the calculator’s default values:
The calculator displays 8.15 cubic yards, 367 eighty-pound bags, and 600 sq ft — matching the math above. For this size pour, ready-mix delivery is the clear choice over 367 bags.
The waste factor covers spillage, over-pour at the edges, an uneven subgrade, and small measuring errors. Order ready-mix in quarter-yard increments — suppliers will not deliver a partial yard, so round 8.15 cu yds up to 8.25 or 8.5 depending on your supplier’s minimum. For bagged concrete, always round up to a whole bag; you cannot buy a partial bag, and running short mid-pour causes a cold joint that weakens the slab.
Use 4 inches for patios, sidewalks, and shed floors; 5–6 inches for driveways and garage slabs that carry vehicles; and 8–12 inches for footings and structural pads. Always check your local building code — many jurisdictions require a minimum thickness and a gravel base for driveways.
A cubic yard of cured concrete weighs about 4,000 pounds, and a full ready-mix truck (10 yards) weighs roughly 40,000 pounds plus the truck. Confirm your driveway and any culverts can handle that load before the truck arrives, or plan to wheelbarrow from the street.
Below about 40°F concrete cures slowly and can freeze before it sets. Use hot mix water, thermal blankets, and an air-entrained mix, and never pour on frozen ground — it will thaw and settle, cracking the slab. In hot weather, the opposite problem applies: work fast and consider a retarding admixture so the slab does not set before you finish it.
Multiply length × width × thickness (in feet) to get cubic feet, then divide by 27 to get cubic yards. Remember to convert thickness from inches to feet first (divide by 12). Add a 10% waste factor for spillage and uneven subgrade.
One cubic yard of concrete equals roughly 45 eighty-pound bags of pre-mix, since each 80lb bag yields about 0.6 cubic feet. There are 27 cubic feet in a cubic yard.
For pours over about 1.5 cubic yards, ready-mix delivery is almost always cheaper and far less labor than mixing bagged concrete by hand. Use bags for small pads, post holes, and repairs.
Pair this estimate with a trade-specific inspection checklist for a clean, verified close-out: Construction closeout checklist.